Home/Data Center Migration/Data center migration readiness checklist

Checklist · free

Data center migration readiness checklist

For IT leaders planning a data center relocation, consolidation or exit: the questions to answer before a move date is set.

Drivers and ownership

#QuestionWhy it matters
1What is driving the move (lease, consolidation, merger or facility risk), and what is the date?The driver and the date set the scope and the pace.
2Who is the executive sponsor, and what result would they count as success?Moves without a sponsor stall when trade-offs arise.
3Who signs off on move windows and on each application's move?Unclear sign-off delays move day.

Inventory and documentation

#QuestionWhy it matters
4How many sites, racks, physical and virtual servers and storage platforms are involved?You can't plan move groups for an estate you can't count.
5How current are your inventories, rack elevations, floorplans and network diagrams?Plans built on old documents fail on move day.
6Are power and cross-connect details documented for the current site?They drive gaining-site design and cabling.
7Are your disaster recovery and business continuity plans current?They are your fallback if a move goes wrong.

Applications and dependencies

#QuestionWhy it matters
8Does every application in scope have a named owner?Owners know the dependencies and approve testing.
9Are shared databases, data feeds, batch jobs and load balancers mapped for each application?Hidden dependencies are the most common move-day surprise.
10Which services cannot go down, and how much downtime can other services tolerate?Tolerance sets move groups and windows.
11Does critical knowledge sit with one or two people?A single absence can stall a move event.
12Which vendors must recertify or support equipment and applications after the move?Recertification needs lead time and planning.

Gaining site

#QuestionWhy it matters
13Has the gaining site been chosen, and is it owned, colocation, cloud or a mix?Many plans depend on the destination.
14Are power, space, connectivity and resilience requirements written down and agreed?Requirements defined late lead to gaps at the new site.
15Are carrier and network requirements known, with their lead times?Circuits often set the earliest possible move date.
16Will the gaining site be ready and tested before the first move event?An unready site turns a move into an outage.

Security and risk

#QuestionWhy it matters
17When were the systems that are moving last scanned for vulnerabilities, and which are out of vendor support?Moving unknown weaknesses carries them to the new site.
18Who will have access during the migration, including third parties, and how will that access be removed afterward?Temporary access is often left open.
19What security controls must the new site meet before go-live?Validation criteria must exist before the move, not after.

Move planning

#QuestionWhy it matters
20Are move groups based on dependencies rather than rack location?Moving dependent systems apart breaks services.
21Will runbooks, validation and rollback plans be tested in dry runs before move day?Rehearsal finds problems while they are cheap to fix.
22Is there a communications and escalation plan, with someone coordinating all teams and vendors?Move day needs one point of control.
23Is post-move support agreed, along with decommissioning and clean-up of the old site?The move isn't finished until the old site is closed out.

How to read your result

  • Mostly "yes": you are ready to set a move date with confidence.
  • Gaps in Applications and dependencies: close these first. They cause most move-day surprises.
  • Gaps in Gaining site: the date may be set by the new site, not by you.
  • Many "don't know" answers: start with discovery and dependency mapping before you commit to a date.

If you found gaps, or a lot of “don’t know” answers, contact Kalosys today, before you commit to a move date. Your note goes straight to our data center migration team.

Talk with our team

Talk to us about your results

Tell us the decision, deadline or problem in front of you.

  1. A reply from the practice that does the workThe practitioners who would deliver it.
  2. A short conversationWhat needs to happen, and by when.
  3. A written proposalWhat you would receive, how long it takes and the fee, before you commit.