Checklist · free
VMware exit readiness checklist
For IT and finance leaders facing a VMware renewal, a datacenter exit or a hardware refresh: what to confirm before you commit to Azure, a renewal or a hybrid path.
Drivers and decision
| # | Question | Why it matters |
|---|
| 1 | Which date is driving the decision (renewal, lease end or hardware refresh), and is it fixed? | The deadline sets how much you can assess before you must act. |
| 2 | Are your VMware, datacenter and hardware support dates listed in one place? | A forgotten date can force a rushed decision. |
| 3 | Who must approve the platform decision and the business case? | Late approvers can reopen settled choices. |
| 4 | What would success look like 12 months from now? | A clear goal keeps cost, risk and speed in balance. |
Inventory and dependencies
| # | Question | Why it matters |
|---|
| 5 | Do you have a verified count of VMs, hosts and clusters, from tools rather than spreadsheets? | Estates usually grow faster than their documentation. |
| 6 | Have you collected performance data over a representative period (at least two weeks)? | Sizing from allocated capacity, not actual use, inflates every option. |
| 7 | Are dependencies between applications, databases and data feeds mapped? | Undocumented dependencies break cutovers. |
| 8 | Does each application have a named owner who can approve its move? | Without an owner, testing and sign-off stall. |
| 9 | Do you know your SQL Server instances, versions and operating system support dates? | Out-of-support systems limit where workloads can go. |
Options and business case
| # | Question | Why it matters |
|---|
| 10 | Have you compared renewing, moving to another on-premises platform, moving to public cloud and a mix, on the same cost and risk basis? | A fair comparison stops the deadline from making the choice for you. |
| 11 | Have you decided, per application, whether to rehost, replatform, refactor, retire or keep it where it is? | Not everything should move, and some things should be retired. |
| 12 | Do you have a cost baseline for today's datacenter and platform? | A business case needs a real starting point. |
| 13 | Is any cloud cost estimate based on measured sizing data? | Estimates built on guesses erode trust in the case. |
| 14 | Have you confirmed current VMware licensing terms for your renewal with your vendor or reseller? | Licensing and packaging have changed in recent years; check before you plan. |
Target platform readiness
| # | Question | Why it matters |
|---|
| 15 | If you already use the cloud, is it governed (identity, policy, network, tagging) before more workloads land? | Moving into an ungoverned foundation adds risk and rework. |
| 16 | Are network bandwidth, latency, DNS and private connectivity (dedicated circuit or VPN) planned, with circuit lead times known? | Connectivity delays often set the real start date. |
| 17 | Do you know which workloads depend on Active Directory or other identity services? | Identity dependencies break sign-in after a move. |
| 18 | Are recovery time and recovery point targets set per application, with a backup plan for the target platform? | Backup and recovery must work on day one, not later. |
Migration approach
| # | Question | Why it matters |
|---|
| 19 | Will a pilot wave of low-risk workloads go first? | A pilot proves the method before critical systems move. |
| 20 | Does every cutover have a test migration and written rollback criteria? | Rollback decided in the moment is rollback done badly. |
| 21 | Are cutover windows, owner sign-off and a support period after each wave agreed? | Users judge the move by the first week after it. |
| 22 | Who owns decommissioning the old platform and the related contract decisions? | Paying for both platforms erodes the savings. |
How to read your result
- Mostly "yes": you are ready to compare options and commit.
- Gaps in Inventory and dependencies: fix those first. Every option depends on them.
- Gaps in Options and business case: you may be about to let the renewal date decide for you.
- Gaps only in the last two sections: plan the foundation and the pilot before the first wave.